Status update – 26/05/2017
Long Term Ash Storage Area Program
- Carting of top soil to the Ash Storage Area recommenced on Monday 22 after weather-related delays.
- Priority areas for top soil spreading are the Southern two bays off access fingers 1 and 2, the Southern “ash borrow pit” area and the Eastern end of access fingers 3 and 4.
- Seven trucks, five D6 dozers, one 30t excavator, one PistenBully and one 45t excavator are working at the site.
- Dust monitors remain in operation to provide real-time data for monitoring and reporting.
Polishing Pond
- Water in the polishing pond has increased following the recent rains. Flinders Power personnel continue to monitor the pond for odour.
Augusta Power Stations Site Enquiries
All public enquiries may be directed to Flinders Power by:
Telephone: 0419 252 760
Email: enquiries@flinderspower.com.au
Additional information can be found at www.flinderspower.com.au
Please Note: The progress reports are issued weekly. Special bulletins/media alerts may be issued from time to time when conditions or circumstances demand it.