Status update re: Augusta Power Stations’ Site – 14 July 2017

Status update – 14/07/2017

Long Term Ash Storage Area Program

  • Carting of top soil to the Ash Storage Area continues.
  • Seven trucks, four D6 dozers, one 30t excavator, one PistenBully and one 45t excavator are working at the site.
  • Dust monitors remain in operation to provide real-time data for monitoring and reporting.

Ash Storage Area Revegetation

  • Native vegetation seeding on the top soil completed on 3 of the 5 top soiled zones last week

Polishing Pond

  • Water in the polishing pond has increased following the recent rains. Flinders Power personnel continue to monitor and manage the pond for odour.

Augusta Power Stations Site Enquiries

  • All public enquiries may be directed to Flinders Power by:
  • Telephone: 0419 252 760
  • Email: enquiries@flinderspower.com.au
  • Additional information can be found at www.flinderspower.com.au

Please Note: Updates are issued fortnightly. Special bulletins/media alerts may be issued from time to time when conditions or circumstances demand it.