Status Update re: Augusta Power Stations’ Site – 28 April 2017
Status Update – 28/4/17 Long Term Ash Storage Area Program The EPA has approved the rehabilitation plans for the ash storage area. Work on applying topsoil continues so that it is in place in time for native vegetation to be established in the coming months. The construction process has progressed to the fifth of a